After a boater signs, most contract terms are locked, but you can still change:
The slip assignment
The contract dates
Discounts and late fees
The rate (monthly contracts only)
Changing the boat on a signed contract is not supported; cancel it and issue a new contract instead. Before signing, you can edit anything on the contract.
Who can do this: Admin, Dockmaster
Where: Contracts → Contracts tab → open the contract, or Customers → customer → Contracts tab
Before you start: Tell the boater about any change to their price or dates; the signed agreement PDF does not change.
What can I change, and where?
Change | Before signing (Unsent / Outstanding) | After signing |
Slip | Edit the contract → Additional Settings → Assignment | Contract view → Assignments section |
Dates | Edit the contract → Itinerary | Billing item Edit → Edit dates (Dates on Custom Installments) |
Rate | Edit the contract → Rate | Billing item Edit → Edit rate (monthly contracts) |
Discounts | Edit the contract → Rate | Billing item Edit → Edit discounts (monthly contracts; Discount on Custom Installments) |
Late fees | Edit the contract → Items and Fees | Billing item Edit → Edit late fees (Late fees on Custom Installments) |
Boat | Edit the contract → customer and boat | Not supported; cancel and create a new contract |
How do I edit a contract that is not signed yet?
Open the contract group and find the contract on the Unsent or Outstanding tab.
Choose Edit from its actions.
Make your changes and click Update customer contract.
If the contract was already sent, the boater's emailed link opens the updated version, but Dockwa doesn't email them about the change. Use Resend if you want them to get a fresh email.
How do I change the slip on a signed contract?
Open the signed contract and scroll to the Assignments section.
Click Add Assignments (or Edit Assignments if the contract already has one). This opens the Assignments page for the contract's reservation, where you assign the new space. To move the boat partway through the season, end the current assignment on the move date and assign the new slip from that date.
Assignments are not emailed to the boater automatically, so let them know their new slip.
How do I change dates or price on a signed contract?
Open the signed contract and find the dockage or storage line on the billing section.
Click Edit on the line (or in the contract header).
In Action, choose Edit rate, Edit discounts, Edit late fees, Edit dates or Create future invoices.
Enter the change and save. Future invoices update; invoices already paid do not change.
The Edit rate option is available on Monthly Installments and Month to Month contracts. On a signed Custom Installments contract, the line's Edit menu offers Dates, Discount and Late fees instead; the rate can't be changed there, so adjust the price with a discount or by adding an item.
Admins can also change the Due date on an unpaid installment invoice from the contract's payments list.
How do I change the boat on a signed contract?
The boat cannot be swapped on a signed contract. Click Cancel Contract at the top of the signed contract (you can choose whether to apply a cancellation fee), then add the customer to the contract group again with the new boat and send a new contract.
Can I end a month-to-month contract?
Yes. Use Edit dates on the billing item to set an end date, or end it right away with Cancel Contract.